Approach: working in a compact team, I gathered the requirements for the move, managed user acceptance testing so teams could confirm everything worked in Jira Cloud, and resolved issues that came up after the migration.
Results: we migrated around 8,500 users and delivered the project 17 days early, despite an accelerated two-month deadline.
Review: after go-live, the review phase used post-migration reports, stakeholder interviews, and surveys to understand how the move had landed for teams. The feedback was positive. It also opened up new conversations about features teams wanted next, which turned into problem-solving meetings and new projects.
Tools and methods: Jira Software, Jira Cloud, requirements gathering, UAT, stakeholder interviews, and surveys.